Boiler Water Circulating Pump – Motor Winding. Practical Guide

Boiler water circulating pumps are critical-duty motors, so winding quality directly affects boiler safety, efficiency, and uptime. Below is a clear, field-oriented explanation useful for rewinding, inspection, and maintenance.

1. Motor Type Commonly Used

  • 3-Phase Squirrel Cage Induction Motor
  • Voltage: 415 V / 6.6 kV / 11 kV (plant dependent)
  • Speed: 1450 RPM or 2900 RPM
  • Duty: S1 (Continuous)
  • Insulation Class: F or H
  • Protection: IP55 / IP65
  • Cooling: IC 411 / IC 416

2. Importance of Proper Winding

Boiler circulating pumps work at:

  • High temperature
  • Continuous load
  • High moisture environment

Poor winding can cause:

  • Overheating
  • Frequent tripping
  • Reduced pump flow
  • Boiler shutdown

3. Winding Specification (Typical)

ParameterDetails
Stator CoreSilicon steel laminations
Winding TypeDouble layer, distributed winding
ConductorElectrolytic copper
InsulationClass F / H varnish
Slot InsulationDMD / Nomex
Phase InsulationPolyester / Nomex paper
ImpregnationVPI / Dip & Bake

4. Rewinding Procedure (Step-by-Step)

Step 1: Pre-Inspection

  • Record original winding data
  • Measure IR & PI values
  • Check bearing and shaft condition

Step 2: Stripping

  • Controlled burning (≤ 350°C)
  • Clean slots thoroughly
  • Check core for hot spots

Step 3: Coil Manufacturing

  • Same turns, pitch & wire size
  • Use high-temperature enamel wire
  • Proper coil forming to avoid stress

Step 4: Winding & Lacing

  • Correct slot filling
  • Proper phase separation
  • Strong end-winding support (critical)

Step 5: Varnish Impregnation

  • Prefer VPI
  • Otherwise Dip–Bake (2 cycles)

Step 6: Testing

  • IR & PI test
  • HV test
  • No-load current test
  • Vibration check after assembly

5. Common Winding Failures & Causes

FailureCause
Insulation breakdownHigh temperature
Phase-to-phase faultLoose end winding
Earth faultMoisture ingress
OverheatingOverloading / poor cooling

6. Recommended Improvements During Rewinding

✔ Upgrade insulation to Class H
✔ Improve end-winding bracing
✔ Use RTD / PTC sensors
✔ Ensure correct bearing clearances
✔ Balance rotor dynamically


7. Best Practices for Long Life

  • Maintain proper boiler water chemistry
  • Ensure pump alignment
  • Avoid dry running
  • Periodic IR testing
  • Keep motor ventilation clean

Boiler Water Circulating Pump Motor Rewinding – Complete Practical Checklist

A. Before Rewinding (Incoming Inspection)

☐ Record motor nameplate details (kW, HP, V, A, RPM, Insulation class)
☐ Note winding connection (Star / Delta)
☐ Measure & record IR values (Phase–Phase, Phase–Earth)
☐ Conduct PI test (for HT motors mandatory)
☐ Check bearing condition & clearances
☐ Inspect shaft run-out & coupling alignment
☐ Verify cooling method (IC 411 / IC 416)
☐ Photograph & note original winding data


B. During Stripping & Core Inspection

☐ Controlled de-varnishing (burning temp ≤ 350°C)
☐ Remove old coils carefully – no lamination damage
☐ Clean stator slots thoroughly
☐ Inspect for core hot spots / shorted laminations
☐ Check stator bore ovality
☐ Perform core loss test (recommended for critical motors)


C. Winding Data Confirmation

☐ Confirm number of slots
☐ Coil pitch & span verified
☐ Turns per coil confirmed
☐ Conductor size & parallel paths verified
☐ Winding type (single / double layer) confirmed
☐ Correct phase sequence planned


D. Insulation Material Checklist

☐ Slot insulation – DMD / Nomex (Class F or H)
☐ Phase separators – Polyester / Nomex
☐ Wedge material – Glass fiber / Epoxy wedges
☐ End winding support – Glass cord / banding tape
☐ Enamel copper wire – Class F / H
☐ Varnish – Thermal Class F / H


E. Winding & Lacing

☐ Uniform coil insertion – no enamel damage
☐ Correct slot fill factor maintained
☐ Phase separation properly maintained
☐ Tight end-winding lacing done
☐ No sharp edges touching insulation
☐ Leads sleeved with fiberglass tubes


F. Impregnation & Drying

☐ VPI preferred for boiler pump motors
☐ If dip-bake:

  • ☐ First dip & bake completed
  • ☐ Second dip & bake completed
    ☐ Oven temperature maintained as per varnish spec
    ☐ Complete curing ensured

G. Electrical Testing After Rewinding

☐ IR test after baking
☐ PI test satisfactory
☐ High Voltage (HV) test passed
☐ Resistance balance test within limits
☐ Phase sequence verified


H. Mechanical Assembly & Checks

☐ Bearings replaced (if required)
☐ Correct bearing greasing done
☐ Rotor dynamic balancing done
☐ Fan & cooling ducts cleaned
☐ Proper air gap maintained


I. Final Trial Run

☐ No-load current within limit
☐ No abnormal noise or vibration
☐ Temperature rise normal
☐ Direction of rotation correct
☐ Cooling airflow verified


J. Documentation & Handover

☐ Test reports attached
☐ Rewinding data sheet prepared
☐ Warranty / guarantee mentioned
☐ Maintenance recommendations given